dc.descriptionEnergi panas bumi menjadi semakin penting di skala global dalam upaya mengurangi ketergantungan pada bahan bakar fosil dan mengurangi dampak negatif terhadap perubahan iklim. Mendapatkan energi dari panas bumi melibatkan sejumlah tahap, di antaranya adalah proses pengeboran sumur panas bumi. Tahap ini adalah salah satu yang paling krusial dalam pengembangan proyek energi panas bumi, mengharuskan efisiensi tinggi dan akurasi agar proyek berjalan dengan sukses Dalam proses pengeboran sumur panas bumi, konsep Productive Time (Waktu Produktif) dan Non-Productive Time (Waktu Tidak Produktif) memiliki peranan yang sangat penting dalam menentukan keberhasilan operasi. Waktu produktif merujuk pada periode di mana proses pengeboran berlangsung efektif dan menghasilkan kemajuan yang signifikan, sedangkan waktu tidak produktif adalah periode di mana operasi terhenti atau berjalan lambat akibat berbagai faktor, seperti masalah peralatan, cuaca buruk, atau kesalahan dalam manajemen operasi. Analisis mengenai Waktu Produktif dan Waktu Tidak Produktif dalam operasi pengeboran panas bumi pada Sumur 'Cool' menjadi fokus utama dalam upaya untuk meningkatkan efisiensi dan mengoptimalkan penggunaan sumber daya. Sumur 'Cool' merupakan salah satu contoh konkret yang menjadi perhatian dalam penelitian ini. Setiap sumur panas bumi memiliki karakteristik unik, termasuk aspek geologis, lingkungan, dan manajemen proyek yang berbeda. Penelitian ini difokuskan pada pemahaman terhadap Non-Productive Time (NPT) terbesar dalam operasi pengeboran panas bumi pada Sumur 'Cool', serta berbagai strategi untuk mengatasinya Hasil penelitian ini diharapkan akan memberikan panduan praktis bagi para profesional di industri energi panas bumi dan pihak-pihak terkait dalam mengidentifikasi akar permasalahan yang sering muncul dalam operasi pengeboran panas bumi di Sumur 'Cool' dan sumur-serumur sejenisnya.en_US
dc.description.abstractThis case study encompasses the entire operational phases of geothermal drilling in the "Cool" well. The drilling operations adhered to a tight schedule, and delays incurred during the process would result in high costs. The majority of workdays in the drilling process were allocated to wellbore construction and supporting activities, contributing to Productive Time (PT). Meanwhile, significant portions of this process were dedicated to addressing unforeseen challenges, leading to Non-Productive Time (NPT). This paper evaluates the extent of Non-Productive Time (NPT) associated with the "Cool" well. Additionally, it identifies the causative factors and impacts of NPT. Ultimately, the paper provides recommendations to enhance Productive Time (PT) while minimizing Non-Productive Time (NPT), thereby improving drilling efficiency. The geothermal drilling process for the "Cool" well consists of four sections. The study reveals that the largest NPT category is RREP, accounting for 74% (47.5 hrs), followed by SFAL at 18% (11.5 hrs), STUC at 5% (3.5 hrs), REAM at 2% (1.5 hrs), and KILL at 1% (0.5 hrs). The total NPT for the "Cool" well is 64.5 hours. The actual operation of the "Cool" well took 47.7 days to reach the Target Depth of 2107 mMD. A comparison with the initial plan shows a savings of 0.3 days to achieve the same depth. In the absence of NPT, the well could have reached the depth in 45.2 days, representing a time savings of 2.5 days. Assuming a drilling operation cost of USD 114,444 per day, the drilling operation could save approximately USD 286,110. These findings underscore the importance of addressing and mitigating NPT to optimize drilling efficiency and reduce operational costs.en_US
dc.language.isootheren_US
dc.subjectproductive time, non-productive time, drilling, casing, cementingen_US
dc.titleAnalisis Productive Time-Non Productive Time Dalam Operasi Drilling Panas Bumi Pada Sumur “Cool”en_US
dc.typeWorking Paperen_US