dc.descriptionKerja Praktik ini dilaksanakan di PT. PLN (PERSERO) UPDK Pekanbaru, PLTG Teluk Lembu. Pada kerja praktik ini membahas dan menganalisa tentang metode perawatan turbin gas pada PT.PLN (PERSERO). Tujuan dari kerja praktik yang telah dilakuan untuk mengetahui metode perawatan turbin gas pada PT. PLN (PERSERO) dan analisis efektivitas dari metode perawatan yang digunakan pada PT. PLN ( PERSERO) UPDK, PLTG Teluk Lembu, Pekanbaru. Pada PLTG Teluk Lembu saat ini menggunakan metode perawatan shut down maintenance karena unit pembangkit pada PLTG Teluk Lembu saat ini lebih sering stand by dan hanya beroperasi pada saat dibutuhkan. Dari hasil perhitungan teoritis diperoleh efisiensi 98.25%, dan setelah dilakukan perawatan dengan metode shutdown maintenance diperoleh nilai perhitungan actual efisiensi turbin gas PLTG Teluk Lembu sebesar 95.50%. Efisiensi dari turbin gas PLTG Teluk Lembu berkurang sebesar 3.75 %. Karena nilai efisiensi dari turbin gas tidak berkurang secara signifikan, dapat disimpulkan untuk saat ini metode perawatan shutdown maintenance masih efektiv untuk kondisi unit stand by dan hanya beroperasi pada saat dibutuhkan.en_US
dc.description.abstractThis practical work is carried out at PT. PLN (PERSERO) UPDK Pekanbaru, PLTG Teluk Lembu. In this practical work discusses and analyzes the gas turbine maintenance methods at PT. PLN (PERSERO). The purpose of the practical work that has been carried out is to find out the gas turbine maintenance method at PT. PLN (PERSERO) and analysis of the effectiveness of the treatment methods used in PT. PLN ( PERSERO) UPDK, PLTG Teluk Lembu, Pekanbaru. PLTG Teluk Lembu currently uses the shut down maintenance method because the generating unit at PLTG is currently more often stand by and only operates when needed. From the results of theoretical calculations, an efficiency of 98.25% was obtained, and after maintenance with the shutdown maintenance method, the actual calculation value of the gas turbine efficiency of the PLTG was obtained by 95.50%. The efficiency of the PLTG Teluk Lembu gas turbine was reduced by 3.75%. Since the efficiency value of the gas turbine has not been significantly reduced, it can be concluded that for now the shutdown maintenance method is still effective for the condition of the stand by unit and only operates when needed.en_US
dc.publisherUniversitas Pertaminaen_US
dc.subjectPerawatan Turbin Gas, Shutdown maintenance, efisiensi Turbin Gasen_US
dc.titleAnalisa perawatan turbin gas type PG 5341 P Unit 3 PT. PLN (PERSERO) Unit pelaksana pembangkit Pekanbaru Riau PLTG Teluk Lembuen_US